Selected References Process Basic Design
Revamping Vacuum LCF
Details
Year
2014
Client
Raffineria di Milazzo S.p.a.
Refinery
Milazzo Refinery
Location
Milazzo - ITALY
Plant
Units 024
Unit Capacity
110753 kg/h
Scope
Verify the vacuum tower, the vacuum tower ejector system, pipes, instrumentation, heat exchanger system at 100% and 120% of design condition and at a new operating pressure of the vacuum tower.
Our Work
- Carry out a thermodinamic simulation of the Vacuum Unit
- Verify existing heat exchanger system
- Verify columns internals
- Design of new equipments (heat exchangers, pipes, PSV, instrumentation)
- Verify the existing hydraulic system at new condition